Lane closures and overnight full shutdowns are set to take place on the Rose Fitzgerald Kennedy Bridge as repair works get underway at Pier 4 from Monday 25 May, with traffic diverted through New Ross Town during full closures.

The works will involve daytime lane restrictions and two full overnight bridge closures from 8pm to 4am on Wednesday 27 May and Thursday 28 May.

Lane 2 closures typically refer to the climbing lanes on either side of the bridge, depending on the traffic management setup.

Rose Fitzgerald Kennedy Bridge closures:

Week 1

Monday 25 May
07:30 to 15:30
Both Lane 2s closed

Tuesday 26 May
07:30 to 15:30
Both Lane 2s closed

Wednesday 27 May
20:00 to 04:00
Full bridge closure overnight

Thursday 28 May
20:00 to 04:00
Full bridge closure overnight

Friday 29 May
No works scheduled, stand down after night shifts

Week 2

Monday 1 June
Public holiday, no works

Tuesday 2 June
07:30 to 15:30
Eastbound Lane 2 closed

Wednesday 3 June
07:30 to 15:30
Eastbound Lane 2 closed

Thursday 4 June
07:30 to 15:30
Both Lane 2s closed

Friday 5 June
07:30 to 14:30
Both Lane 2s closed

Week 3

Monday 8 June
07:30 to 15:30
Both Lane 2s closed

Tuesday 9 June
07:30 to 15:30
Westbound Lane 2 closed

Wednesday 10 June
07:30 to 15:30
Westbound Lane 2 closed

Thursday 11 June
Times and closures to be confirmed
Possible westbound or both Lane 2s closed for finishing works

Friday 12 June
Times and closures to be confirmed
Possible both Lane 2s closed for final finishing works